Open-Air Laundry Area With A Transparent Roof

 

Detailed Breakdown of Costs:

Materials:

  1. Concrete Works:

    • Cement (bags): 20 bags @ PHP 250 each = PHP 5,000

    • Sand (cubic meters): 2 cubic meters @ PHP 1,500 each = PHP 3,000

    • Gravel (cubic meters): 2 cubic meters @ PHP 1,500 each = PHP 3,000

    • Concrete hollow blocks (pcs): 150 pcs @ PHP 15 each = PHP 2,250

    • Steel bars (pcs): 15 pcs @ PHP 500 each = PHP 7,500

  2. Roofing:

    • Transparent roofing sheets (pcs): 8 pcs @ PHP 1,200 each = PHP 9,600

    • Wood for framing (board feet): 80 board feet @ PHP 50 each = PHP 4,000

  3. Flooring and Walls:

    • Tiles for flooring (sqm): 8 sqm @ PHP 500 each = PHP 4,000

    • Tiles for walls (sqm): 15 sqm @ PHP 500 each = PHP 7,500

  4. Plumbing:

    • Pipes and fittings: Estimated = PHP 3,000

    • Drainage system materials: Estimated = PHP 2,000

  5. Electrical:

    • Wiring, switches, and outlets: Estimated = PHP 2,000

    • Lighting fixtures: Estimated = PHP 2,500

  6. Finishing Materials:

    • Paint (liters): For both interior and exterior surfaces = PHP 3,000

    • Miscellaneous materials: Sealants, adhesives, etc. = PHP 2,500

  7. Shelves and Fixtures:

    • Wood for shelves: 30 board feet @ PHP 50 each = PHP 1,500

    • Fixtures (sink, taps, etc.): Estimated = PHP 5,000

  8. Green Plants and Landscaping:

    • Plants and soil: Estimated = PHP 2,000

Total Materials Cost: PHP 64,350

Labor:

  1. Skilled Labor:

    • Masons, Carpenters, Tilers, Plumber, Electrician, Painter

    • 5 days @ PHP 800/day each = PHP 24,000 (assuming 6 skilled workers)

  2. Unskilled Labor:

    • Helpers to assist skilled workers

    • 5 days @ PHP 500/day each = PHP 10,000 (assuming 4 helpers)

Total Labor Cost: PHP 34,000

Overhead and Profit:

  1. Overhead (10% of materials and labor): PHP 9,835

  2. Profit (15% of materials and labor): PHP 14,752.50

Contingency and Miscellaneous:

  • Additional contingency for unforeseen expenses and additional scope: PHP 52,062.50

Grand Total:

PHP 200,000.00

Notes:

  • This estimate is based on standard prices and may vary depending on actual market prices and availability of materials.

  • The labor cost includes a slightly higher rate to ensure quality work and timely completion.

  • Overhead and profit percentages ensure the project is profitable while covering all additional expenses.

  • The contingency amount provides a buffer for any unforeseen costs or additional work not initially covered.

Comments

Popular Posts

Understanding Construction Labor Rates in the Philippines

A Journey of Trust and Redemption: Reflections on My Life's Challenges

Get A Customized Home Builder! In Cagayan de Oro. Trusted Contractor.

6 Effective Tips for Healthy Arguments in Relationships: Keep Love Alive

Cagayan de Oro Home Services

The Builders Lesson of 2023: The Art of Letting Go